• Email
  • Print

Park Road I-84 Project

What's New

Construction on Park Road at the I-84 interchange is nearing completion! Final paving was completed in early September and most of the landscaping has been installed. The remaining work should be wrapped up in October and includes: guiderails, pavement markings, signage, and any punch-list items. These activities should be completed with only minor traffic impacts and temporary lane closures. The timing of the traffic signals will also be fine-tuned over the next several weeks to improve coordination and operation.

 

Thank you to the motoring public and especially the nearby residents for your continued patience and cooperation throughout this project.

For a live look at the progress, please click the ‘Live Cam’ link on the menu bar on the left side of the screen.

Construction Live Cam provided by iBEAM Construction Cameras 

 By the Numbers
30,000 Average Vehicles Per Day 
17,300 Cubic Yards of Earth to be moved
13,700 Tons of Asphalt
7,500 New Sidewalk (in square feet)
400 Calendar Days to Complete the project
280 New Trees to be planted
41, 42 or 44 Alternate Highway Exits during Construction
$6.8 Million Project Cost
3 New Traffic Signals